FOR AVERAGE PROJECTS, WE ARE ONLY IN YOUR HOME FOR 3 ½ DAYS
We are not a typical contractor. We can guarantee that we will complete your job within the week of your start date. See a sample of our most typical timeline below
-
MON
MONDAY
We arrive at your home at about 8-9 a.m. We spend Monday prepping your kitchen.
-
TUES
TUESDAY
We finish prep and apply 2-4 coats of primer.
-
Just 3.5 Days in your home.
-
WED
WEDNESDAY
We sand the primer smooth, fix imperfections and apply the finish coats.
-
THU
REINSTALL DOORS & DRAWERS
We clean up the masking and reinstall doors. You can use your new kitchen now!